Constructing the Pre-School
Staring on Monday 6th January 2020, local builders W H Hodder and Son will be developing 2 classrooms in our school to create a new EYFS Hub which will incorporate a Pre-School, a Reception Classroom and a shared outdoor space.
Just Finished - A couple of short videos
Our Designs
Phase 1 - New Reception Classroom
We are transforming the spare classroom which is next to our current Reception Classroom. This will be ready for Robins Class to move in to at the start of February.
Can you spot all of the changes?
Before the Works


During Week 1

At the end of Week 2

End of Week 3

Week 4
Children will be moving in very soon indeed....

End of Week 4 - all moved in!

Phase 2
We are transforming the old Reception classroom. This will be ready for prospective Parents and Carers to view around Easter time.
Can you spot how the room has transformed?
Before the Works

Middle of Week 2


Middle of Week 4

End of Week 6


All Finished - Friday 20th March 2020

.jpg?width=1920&height=1080&scale=LIMIT_MAXSIZE)
Outside area
We are also redeveloping the outside space for the Pre School and Reception pupils to use.